Recently, CADI-SUN have continued to become the first choice of Nguyen Tam partner, honored to contribute to the success of the 500 kV Transmission Line Quang Trach - Quang Binh Thermal Power Plant.

Nguyen Tam Construction and Trading Joint Stock Company is a supplier of electric cables with more than 10 years of experience, and has affirmed its reputation in the market with high quality products. For electric cables, in the past years, Nguyen Tam has always chosen the brand of CADI-SUN because this is a prestigious manufacturer, owning a factory, a modern equipment line which is invested synchronously from Europe.

Through the time of strong cooperation between the two sides, CADI-SUN’s electric cables products have become a reliable “companion” with Nguyen Tam in many big works and projects of the National. Typically, according to the information on daycap.com.vn: “At the beginning of 2020, the 500 kV transmission line Quang Trach - Vung Ang thermal power plant and the 500 kV distribution yard of Quang Trach Power Center; the 500 kV transmission line Quang Trach - Doc Soi and the 500 KV transmission line Doc Soi - Pleiku 2 were assigned by Vietnam Electricity (EVN) to the National Power Transmission Corporation (EVNNPT) as the Employer, and Central Power Projects Management Board (CPMB) on behalf of EVNNPT to manage the project. These are urgent electrical projects in the National Electricity Development Planning with the goal of transmitting electricity from Quang Trach Power Center to the National Electricity System. At the same time, strengthening the transmission capacity of the 500 kV electrical grid linking regions of the national electricity system, making an important contribution in ensuring power supply to the South in the coming time as well as being important in the economic operation of the national electricity system ”.

CADI-SUN participated in Package of the 500 kV Transmission Line Quang Trach - Quang Binh Thermal Power Plant

 
Delegates conducted the groundbreaking ceremony  

The overall scale of the 3 projects includes: Building nearly 742 km of 500 kV double circuit lines passing 9 provinces/cities (Ha Tinh, Quang Binh, Quang Tri, Thua Thien - Hue, Da Nang, Quang Nam, Quang Ngai, Kon Tum, Gia Lai); Constructing 08 500 kV feeders at the distribution yard of Quang Trach Power Center; Expanding a number of 500 kV feeders at 500 kV Vung Ang, Doc Soi and Pleiku 2 transformer stations; Constructing 03 fiber optical repeaters and 03 management houses to manage electricity transmission teams.

CADI-SUN participated in Package of the 500 kV Transmission Line Quang Trach - Quang Binh Thermal Power Plant


Products of CADI-SUN are trusted in key projects

Total investment of all projects is invested over VND11,949 billion, expected construction time of all projects is about 20 months and strives to be completed and put into operation in the middle of 2020./.